Update on the Ten Year Refit and Service

We are 4 weeks in to this major piece of work. So far, the boat has been stripped down, the deck has been removed for recoating, the fuel tanks have been cleaned and pressure tested and all fuel lines and hoses have been replaced. The tow post and anchor locker have been removed for modifications and repainted. The console has had corrosion removed and powder coated. The hull has had some gel coat repairs and a polish, so it is looking like new.

The new 200 hp Mercury engines are now fitted and the boat is being put back together. We are still hopefully on track for delivery by the end of the month. The only issue at the moment is that the company that is making the new console is behind schedule, but they are under pressure to get this done on time.